Regional View

A map showing the location and status of regional projects, and some within the City of Colorado Springs, for the second renewal of the Pikes Peak Rural Transportation Authority.
Click here for an accessible version of the regional view map

1. Black Forest Rd. Roadway Improvements: Woodmen Rd. to Research Pkwy. $30,793,970

2. Stapleton Dr./Briargate Blvd. Corridor Study $1,100,000

4. W. Colorado Ave. Reconstruction: 31st St. to US 24 $36,918,648

12. Beacon Lite Rd.: Highway 105 to Countyline Rd. $21,978,986

13. Belvedere Ave. Widening Phase I (Green Mountain Falls) $226,000

15. Centennial Blvd.: Garden Of The Gods Rd. to Fillmore St. Pavement Reconstruction $12,287,810

23. Cottonwood Trail Corridor Improvements $600,000

24. Deer Creek Rd., Base Camp Rd., Emigrant Tr.: Monument Hill Rd. to Woodmoor Dr. $4,459,421

26. Eastonville Rd.: Mclaughlin Rd. to Latigo Blvd. $16,948,186

27. 8th St. Improvements.: Motor City Way to Fountain Creek $4,577,083

32. Fontaine Blvd. At Security Blvd. and Widefield Blvd. $1,750,000

34. Highway 105: I-25 to Highway 83 $30,750,034

39. Manitou Ave. West End Pedestrian and Drainage Improvements $1,600,000

40. Manitou Springs Downtown Sidewalk, Drainage and Utilities Improvements $1,500,000

41. Manitou Springs Transit Shuttle and Surface or Structure Parking $1,901,281

42. Meridian Rd./Mclaughlin Rd. Roundabout $4,480,184

43. Mesa Ridge Pkwy. Improvements: Powers Blvd. to Marksheffel Rd. $10,014,997

45. Monument Hill Rd.: County Line Rd. to Woodmoor Dr. $11,683,852

46. New Meridian Rd. At US-24 $5,103,816

47. Old Ranch Rd. Improvements And Bridge construction $10,031,668

51. Pikes Peak Greenway Corridor Improvements $7,700,000

53. Platte Ave. Corridor Improvement Study $2,000,000

55. Ramah: Street Overlay Program $82,584

58. S. Cheyenne Canyon Rd. 1 Over Cheyenne Creek Bridge Replacement $3,467,898

63. Sinton Trail Corridor Improvements $825,000

64. Stilling Basins (Roadway Drainage Improvements) $582,580

65. Templeton Gap Trail Corridor Improvements $825,000

71. Woodmen Rd. Improvements: Union Blvd. Continuous Flow Intersection. $9,000,000

Projects Not Mapped

ADA-Paratransit Bus System Vehicle Replacement $3,091,051

Companion Drainage Improvements for Roadway Projects $3,708,000

Congestion and Incident Management Signal Improvements Phase I $4,531,970

Emergency Bridge Fund $20,040,638

Enchanted Cl. Over Sand Creek Tributary Bridge Replacement $500,000

Fixed-Route Bus System Vehicle Replacement $8,557,917

Intersection Improvements Phase I $14,064,697

On Street Bikeway Improvements Phase I $5,132,727

Pedestrian Transportation Improvements Phase I $7,833,635

Roadway Safety and Traffic Operations Phase I $27,976,876

School & Neighborhood Pedestrian Improvements Phase I $4,531,970

Sidewalk/Bus Stop program existing Routes $2,020,000

Traffic Signal System Upgrade (60 Locations) $12,626,103

Vanpool Vehicle Replacement $1,070,001

City of Colorado Springs

A map showing the location and status of projects within the City of Colorado Springs for the second renewal of the Pikes Peak Rural Transportation Authority.

3. Tutt Blvd. Extension: Dublin Blvd. to Templeton Gap Rd. $5,279,518

4. W. Colorado Ave. Reconstruction: 31st St. to US 24 $36,918,648

5. Academy Blvd.: Bijou St. to Airport Rd. Pavement Reconstruction $15,985,734

6. Academy Blvd.: Fountain Blvd. to Milton Proby Pkwy. Pavement Reconstruction $49,029,331

7. Academy Blvd.: I-25 to Bradley Rd. Ramps $67,039,294

8. Academy Blvd. Over Cottonwood Creek Bridge Rehabilitation $9,180,000

10. Airport Rd. Over Spring Creek Bridge Replacement $6,159,595

11. Barnes Rd. Roadway Improvements: Solar Ridge Dr. to Powers Blvd. $4,050,000

14. Centennial Blvd. Extension: Fillmore St. to Fontanero St. $26,630,629

15. Centennial Blvd.: Garden Of The Gods Rd. to Fillmore St. Pavement Reconstruction $12,287,810

16. Chestnut St. Over S. Douglas Creek Bridge Replacement $4,162,926

17. Circle Dr. Eastbound Over Fountain Creek Bridge Rehabilitation $11,301,000

18. Circle Dr. Eastbound Over Hancock Bridge Rehabilitation $11,301,000

19. Circle Dr. Westbound Over Fountain Creek Bridge Rehabilitation $11,301,000

20. Circle Dr. Westbound Over Hancock Bridge Rehabilitation $11,301,000

23. Cottonwood Trail Corridor Improvements $600,000

25. Dublin Blvd. Improvements: Bridle Pass Way to Powers Blvd. $2,029,165

27. 8th St. Improvements.: Motor City Way to Fountain Creek $4,577,083

28. El Paso Blvd. Bridge Over Fountain Creek Tributary Replacement $1,497,600

30. Enchanted Circle Over Sand Creek Tributary Bridge Replacement $500,000

32. Fontaine Blvd. At Security Blvd. and Widefield Blvd. $1,500,000

33. Galley Rd. Over Sand Creek Bridge Replacement $6,106,378

35. I-25 Ramps: South Nevada Ave./Tejon St. Corridor Improvements $9,111,497

37. Las Vegas St./Royer Union Pacific RR Crossing Relocation $14,755,238

38. Main St. at Security Blvd. $750,000 44. Midland Trail Improvements: Ridge Rd. to Columbia St. $450,000

50. Pikes Peak Ave.: Colorado Ave. to Printers Pkwy. Pavement Reconstruction $16,077,754

51. Pikes Peak Greenway Corridor Improvements $7,700,000

52. Platte Ave. Connection to I-25 Study $550,000

53. Platte Ave. Corridor Improvement Study $2,000,000

54. Platte Ave. Westbound Over Sand Creek Bridge Replacement $4,634,000

57. Rock Island Trail Corridor Improvements $1,000,000

58. S. Cheyenne Canyon Rd. 1 Over Cheyenne Creek Bridge Replacement $3,467,898

60. Shook’s Run Bridge Corridor Study $2,750,000

61. Shook’s Run Trail Corridor Improvements $800,000

63. Sinton Trail Corridor Improvements $825,000

65. Templeton Gap Trail Corridor Improvements $825,000

67. Union Pacific RR Mainline Over Fontanero St. Bridge Replacement $21,377,495

68. Union Pacific RR Nevada and Tejon St. Crossing Reconstruction (Design Only) $5,050,000

70. W. Fillmore St. Over Unnamed Channel Bridge Replacement $3,394,469

71. Woodmen Rd. Improvements: Union Blvd. Continuous Flow Intersection. $9,000,000