2025 Annual Report – Colorado Springs Maintenance Projects

Roadway Maintenance

PPRTA roadway maintenance focuses on preventative measures to preserve the integrity of infrastructure within the City’s right-of-way. Regular maintenance helps prolong the life of city infrastructure and reduces the need for costly repairs in the future. Roadway maintenance activities in 2024 included:

  • Concrete Maintenance:
    • On Call & ADA: $9,561,369 in maintenance efforts, year-over-year (YoY) increase of $324,837.
    • Cost Share: $68,583 in maintenance efforts, YoY decrease of $19,861.
    • Sidewalk Vertical Displacement Mitigation: $214,533 in maintenance efforts, YoY increase of $26,189.
    • Truncated Domes: $174,572 in maintenance efforts, YoY increase of $18,050.
  • Roadway Maintenance:
    • Slurry Seal: $968,499 in maintenance efforts, YoY decrease of $342,484.
    • Chip Seal: $2,053,504 in maintenance efforts, YoY increase of $575,086.
    • Crack Seal: $1,111,603 in maintenance efforts, YoY decrease of $331,959.
    • Dig Out and Wide Crack Mitigation: $612,686 in maintenance efforts, YoY increase of $78,164.
  • Additional Maintenance:
    • Pipe: $515,484 in maintenance efforts, YoY decrease of $1,034,442.
    • Guardrail: $146,451 in maintenance efforts, YoY increase of $45,713.

In 2024, efforts continued for three special projects:

  • Structures in the Right-of-way (a partnership with City Engineering): $419,726 in maintenance efforts, YoY decrease of $293,691.
  • Rustic Hills – Phase 2 (a partnership with City Engineering): $2,112,205 in maintenance efforts, YoY increase of $752,159.

Project Details:

  • Installation of ADA compliant pedestrian ramps.
  • Sidewalk repairs improve accessible routes to foot traffic.
  • Curb, gutter, and cross pan repairs.
  • Inlet installation to improve drainage.
  • Median removals to improve roadway drainage.
  • Roadway profile adjustments in localized areas to improve drainage.

Highlights of efforts in 2024:

  • Chip Seal Program
    • 388,958 square yards placed.
    • 60 lane miles completed.
  • Dig Out and Wide Crack Mitigation Program
    • Contracted Programs: 1,345 tons of asphalt material placed.
    • In-House Programs: 15,030 tons of asphalt material placed.
  • Crack Seal Program
    • Contracted Programs:
      • 538,289 pounds of crack sealant applied.
      • 119 lane miles of roadway impacted.
    • In-House Programs:
      • 127,272 pounds of crack seal material applied.
      • 28 lane miles of roadway impacted.
  • In-House Pothole Repair Program
    • 94,331 potholes filled.
  • Contracted Programs Sidewalk Vertical Displacement Program: 2,435 total cuts
  • On-Call & ADA Program
    • 50,795 linear feet of curb and gutter.
    • 186,345 square feet of sidewalk.
    • 181 new pedestrian ramps.
    • 105 retrofitted pedestrian ramps.
    • 57 cross pans.
  • Cost Share Concrete Totals
    • 367 linear feet of curb and gutter.
    • 4,537 square feet of sidewalk
  • Guardrail Totals: 15 projects completed
Crews working on a bridge project

Bridge Maintenance

PPRTA funding is used to plan and perform bridge maintenance activities to the City’s 233 major bridge structures (greater than 20 feet in length) and 231 minor bridge structures (between four feet and 20 feet in length). Since the beginning of PPRTA in 2005, the funding provided by PPRTA for bridge maintenance has been invested to address several types of maintenance efforts as described below. This investment has enabled the City to move its efforts from mostly emergency responses to a deliberate and planned bridge maintenance effort. The benefit to the community includes improvements in safety and a reduction in the loss of the use of bridges.

Highlights:

Performed, contracted, and completed bridge maintenance construction activities on 52 bridges. These activities were focused on repair, safety, engineering, and programmed preventative maintenance. Most significant efforts included:

  • Continued design of Cache La Poudre over Monument Creek Bridge Rehabilitation.
  • Continued design of 25th Street Bridge Rehabilitation.
  • Completed bridge preventative waterproofing maintenance on 13 structures.
  • Performed guardrail repair at 10 locations.
  • Performed Enhanced Inspections at 15 structures.
  • Continued update on Bridge Asset Management Plan and identified most needed projects in next 15 years.
  • Updated and improved the Bridge Maintenance 5-Year Plan.