8th Street – Motor City Way to Fountain Creek
The project will develop a range of possible safety, traffic operation, and multimodal improvements along with updating the deteriorated infrastructure. The project will prioritize implementation strategies to achieve goals while staying within the budget. The project is currently advancing the selected improvements through engineering and into construction. PPRTA budget is $4,577,083.
Highlights:
- Continued meetings with property and business owners to address concerns.
- Working with Colorado Springs Utilities to combine efforts to install a 24” water transmission line.
- Planning a bore under US-24 and Bear Creek for the waterline scope to reduce impacts to the traveling public.
- Coordinating with the City Bridge Maintenance Program to accommodate widening of the 8th Street bridge over Fountain Creek and intersection improvements between the creek and US-24.

Academy Boulevard Pavement Reconstruction – Fountain to Milton Proby Parkway
Academy Boulevard between Fountain Boulevard and Milton Proby Parkway is a six-lane road with poor pavement, curb, gutter, and median conditions that require replacement. The project length of 12,490 feet includes remediation of the pavement area that experiences subsidence due to an abandoned landfill. Poor drainage is also contributing to pavement decline, so a new storm water system is being designed to alleviate ponding issues. Planned improvements incorporate recommendations from the Great Streets Corridor Study including a 10-foot-wide multi-use path. PPRTA budget is $49,029,331.
Highlights:
- Notice-to-proceed issued to contractor in February 2023.
- A 24-inch water transmission line is installed between Drennan and Hancock Expressway.
- Installed a new median in Hancock Expressway east of Academy Boulevard.
- Descoped the remainder of the construction contract and will be rebid in 2025.

Academy Boulevard Pavement Reconstruction – Bijou to Airport
Academy Boulevard between Bijou Street and Airport Road is 4,700 feet and six-lanes wide. The roadway has poor pavement, curb, gutter, and median conditions that require replacement. Poor drainage is also contributing to pavement decline, so a new storm water system is being designed to alleviate ponding issues. Planned improvements incorporate recommendations from the Great Streets Corridor Study, including a 10-foot-wide multi-use path. PPRTA budget is $15,985,734.
Highlights:
- Notice-to-proceed issued to contractor in February 2023.
- Installed a 24-inch water transmission line from Airport Road to Pikes Peak.
- Storm drains installed in Academy.
- Curb and gutter and sidewalk construction completed on the east and west side of Academy south of Pikes Peak.
- Installed a 42-inch sewer and 12-inch water in Airport Road.
- Construction completed December 2024.

Black Forest Road Roadway Improvements – Woodmen to Research
The project will widen Black Forest Road to a four-lane principal arterial cross-section from Woodmen Road to Research Parkway, including a new bridge over Cottonwood Creek. The existing and proposed development in the City and the County require more capacity on Black Forest Road than the current two-lane section provides. PPRTA budget is $30,793,970.
Highlights:
- Construction substantially completed December 2024.
- Work on the Cottonwood Creek Tributary began in November 2023 and was completed July 2024.

Circle Drive Bridges Over Hancock and Fountain Creek Rehabilitation
Constructed by the Colorado Department of Highways in 1963, the Circle Drive bridges carry eastbound and westbound lanes of Circle Drive on separate structures. The western pair of bridges cross Fountain Creek. The eastern pair of bridges cross the BNSF Railway, a Fountain Mutual Irrigation Company conveyance facility, Hancock Expressway, and East Las Vegas Street. This project will replace the structures with four new bridges. The new bridges will have wider cross sections to allow for better pedestrian movement. PPRTA budget is $45,204,000.
Highlights:
- Phase 1 was completed in December 2024.
- Completed traffic shift to new eastbound bridges.
- The demolition of the westbound bridges has begun.

El Paso Boulevard Over Fountain Creek Tributary Bridge Replacement
El Paso Boulevard Over Fountain Creek Tributary Bridge Replacement Project proposes to replace an aging bridge structure crossing over a tributary to Fountain Creek commonly known as the Columbia Road Tributary. Recent bridge inspections have determined the structure to be ‘functionally obsolete’ and qualify the bridge for replacement. The bridge is in the west side of Colorado Springs on El Paso Boulevard, approximately 800 feet north of West Colorado Avenue and 200 feet west of South Columbia Road. The bridge is approximately 500 feet east of the Manitou Springs city limit. PPRTA budget is $1,497,600.
Highlights:
- Completed the bridge replacement within contract budget and schedule.
- Resolved all utility conflicts with affected utility owners.
- Within the available budget, the project was able to expand the limits of pavement overlay
to improve the corridor. - Coordinated bike lane markings and pavement striping to extend into Manitou Springs.

Galley Road Over Sand Creek Bridge Replacement
The Galley Road Bridge was built in 1965 and replacement is needed as this bridge is both too narrow for the roadway and hydraulically inadequate. The Federal Emergency Management Agency floodplain mapping shows the road overtops, and there have been reports of overtopping by 3-4 feet in recent years. The replacement approach from the alternatives analysis is to widen the road to match road section on either side of the bridge and build a new, deeper concrete box culvert with drop structures to provide adequate capacity in the channel. The West Fork of the Sand Creek channel invert will be lowered to provide adequate room for flows. An at-grade, pedestrian actuated traffic signal will be provided for the trail crossing at Galley Road. The project will also combine Colorado Springs Utilities waterline work and mill and overlay work within the project area. PPRTA budget is $6,106,378.
Highlights:
The project was issued for bid in September 2023 and the contractor was selected to start work in 2025 for the combined bridge and waterline work.
- In spring 2024 the area communications companies and Colorado Springs Utilities began the pre-project work as the project carries a vast amount of public and private utilities.
- Temporary right-of-way agreements were negotiated and accepted by adjacent property owners.
- Construction is planned for spring 2025 with a 6–8-month duration.
Citywide Congestion and Incident Management Signal Improvements Phase I
Implement Citywide/Region wide Intelligent Transportation Systems to improve traffic operations, coordinate systems, and improve safety. Improvements may include monitoring systems, hardware and software, message systems, metering, communication infrastructure, and specialized equipment and staff.
Highlights:
- Purchase of signal controllers.
- Upgrades to traffic safety software, traffic operations analysis software, and traffic data access.
- Purchase of signal cabinets.

I-25 Ramps – South Nevada and Tejon Street Corridor Improvements
The intersections of the I-25 ramps at South Nevada Avenue and South Tejon Street typically experience reoccurring traffic incidents, conflicts, and congestion during peak weekday and weekend travel times. The City and Colorado Department of Transportation have studied and implemented improvements in the South Nevada Avenue and South Tejon Street corridors over time. This project is the latest effort in improving efficiency and safety for all modes of traffic based on current conditions. PPRTA budget is $9,111,497.
Highlights:
- Project construction to begin in spring 2024.
- Pedestrian Bridge at the south I-25 Connector Road is in place.
- Project construction anticipated to complete in spring 2025.

Las Vegas Street and Royer UPRR Crossing Relocation
The Royer Street railroad crossing is non-standard and restricts the clearance of low-profile vehicles. The Federal Railroad Administration has recorded 25 non-fatal, “train vs. vehicle” accidents at this crossing since 1975. A new road and rail crossing, Twin Bridges, will be constructed to replace the Royer Street rail crossing. Twin Bridges Road will begin at the existing traffic signal for the entrance of the Leon Young Colorado Springs Utilities Facilities on Hancock Expressway and cross the rail to the south, passing under the US-24 (Martin Luther King Bypass), and connecting to Las Vegas Street just east of the bypass. The new roadway and rail crossing will be operational prior to the closure of the existing crossing at Royer Street. PPRTA budget is $14,755,238.
Highlights:
- Construction Request for Proposals issued and bidding complete.
- Three-party City, Union Pacific, and BNSF Railways Agreement initiated and under review.
- Construction contract to be issued in 2025.

Platte Avenue Corridor Improvement Study
including Connection to Interstate 25 The Platte Avenue Corridor is one of the major transportation corridors in the City of Colorado Springs. In recognition of this, the City included a focused study of transportation improvement needs for Platte Avenue between Powers Boulevard and downtown. A greater understanding of how the community uses Platte Avenue and the surrounding transportation connections provides a valuable opportunity to improve how people travel by car, transit, walking, or biking in and around this six-mile corridor. PPRTA budget is $2,000,000.
Highlights:
- Project study is complete.

South Cheyenne Canyon Road Over Cheyenne Creek
Bridge Replacement Believed to be built in 1957, the original South Cheyenne Canon Road Bridge was a multi-type structure located just north of the Seven Falls entrance. The bridge was load-posted and had reached the end of its service life, requiring replacement. This project provided a new roadway bridge and a pedestrian/trail bridge for better flow and safety. The new roadway structure is 75 feet east of the original structure and the pedestrian bridge aligns with the Chamberlin Trail system. PPRTA budget is $3,467,898.
Highlights:
- The project was issued for bid in September 2023, and the contractor started work in January 2024.
- The project was completed in July 2024 and has received a fair amount of praise on its aesthetics and trail improvement.

Tutt Boulevard Extension – Dublin to Templeton Gap Road
The Tutt Boulevard extension project is a joint PPRTA Colorado Springs/El Paso County project. Tutt Boulevard was extended North from Dublin Boulevard and connects with the existing Tutt Boulevard, approximately 1,000 feet North. Phase 1 (from Dublin Boulevard to Vickie Lane) was completed in March 2016. Final engineering of Phase 2 commenced in July of 2021 and followed by land acquisition through 2023. Construction took place in spring 2024 and was completed in August 2024. PPRTA budget is $5,279,518.
Highlights:
- Phase 1 was completed in 2016.
- Construction documents were finalized and issued for bid in January 2024.
- Construction began in late spring 2024 and was completed in fall 2024.
- The project improved the flow and safety in the area by removing an intersection, adding two additional lanes to match the roadway on either side and connecting to the first phase from Dublin Boulevard.

Dublin Boulevard Improvements – Peterson Road to Marksheffel Road
This project will make improvements to Dublin Boulevard from approximately Peterson Road to Marksheffel Road. Improvements include widening the existing roadway from one lane in each direction to two lanes in each direction with a raised median and multi-use shoulders per the City standard section for principal arterial roadways. PPRTA Traffic Program funds were used to start engineering on the project and PPRTA capital budget is: $16,600,000.
Highlights:
- Consultant completed 90% engineering documents in 2024 and will deliver plans for bid in
February 2025. - Construction will be completed with Marksheffel Road.

UPRR Nevada and Tejon Street Crossing Reconstruction (Design Only)
This important project, formerly known as PPRTA “A” list UPRR Nevada Avenue and Tejon Street Crossing Reconstruction (Design Only)” project, is now referred to as the South Downtown Rail Underpass Reconstruction project. The project aims to address safety and operational issues along the rail corridor and improve transportation connectivity for all travel modes in the south downtown area. The project would replace the two railroad bridges at South Nevada Avenue and South Tejon Street, along with the railroad bridge and Las Vegas Street roadway bridge over Shooks Run. The work along Shooks Run would facilitate a grade-separated trail crossing to complete the Legacy Loop Trail system. The project also includes roadway, stormwater, and other associated improvements.
In June 2022, the City was awarded a $2.5 million federal grant under the Federal Railroad Administration’s Fiscal Year 2021 Consolidated Rail Infrastructure and Safety Improvements program to fund the environmental and preliminary engineering phase of the project. Future construction will focus on the replacement of the aging railroad bridges over South Nevada Avenue (76-years-old) and the South Tejon Street (122-years-old) which are in poor condition. PPRTA budget is $5,050,000; $2,500,000 federal. The objective of the current phase of the project is to secure environmental clearance, prepare preliminary engineering design, and position the project for future funding opportunities.
BNSF Railway is planning to replace the railroad bridge over Tejon Street in its existing location due to its condition. Design and construction of this project is funded entirely by BNSF Railway and is expected to begin as early as April 2025 and be complete by October 2025.
Highlights:
- City was awarded a Federal Railroad Administration grant in June 2022 for Preliminary Engineering and National Environmental Policy Act work. Environmental Review and Preliminary Engineering is in progress.
- City and consultant have processed 10% review comments by the railroads and are preparing for a resubmittal of the 10% plan package.
- Ongoing stakeholder outreach and public engagement activities.
- BNSF Railway is planning to replace the railroad bridge over Tejon Street in its existing location due to its condition. Design and construction of this project is funded entirely by BNSF Railway. Construction is expected to begin as early as April 2025 and be complete by October 2025.

Union Pacific Railroad Mainline Over Fontanero Bridge Replacement
The goal of this project is to replace the mainline track railroad bridge over Fontanero Street just east of I-25. The Union Pacific Railroad Mainline over Fontanero Bridge was built in 1963. The driving need for this project is the inadequate strength of the existing mainline railroad bridge. In addition, the clearance under the bridge is inadequate because it is 1 to 6 feet less than current standards, which is a safety issue proven by the truck impacts on the bridges. Temporary supports were constructed under the end spans as a PPRTA Bridge Maintenance effort in 2012 to partially address the strength issue. Since the supports were not able to increase the strength fully, the intent was to address the bridge strength issue only as an interim solution. The agreement with the railroad to construct the temporary supports requires the City to replace the bridge.
As shown in the photo, there is a second railroad bridge which carries a railroad siding track immediately to the east of the mainline track railroad bridge. The siding bridge was also built in 1963 and has the same issues with strength and clearances, along with the same commitments to the railroad. The City recognizes and respects the fact that the siding bridge is a B-list project. The design effort for the siding bridge is being advanced using the Emergency Bridge Fund at the same time as the mainline railroad bridge design.
Preliminary engineering identified the necessity to reconstruct both the mainline and siding bridges as one construction project. The design also shows that the road will need to be lowered approximately four feet at the existing bridges, which impacts the existing bridge foundations. Railroad operations are required to continue during construction, and both the mainline and siding bridges are needed for rail detours, thus requiring the City to advance the UPRR Siding over Fontanero project with the mainline A-list project. PPRTA budget is $21,377,495.
Highlights:
- Railroads have agreed to short-duration closures of each track to facilitate Accelerated Bridge Construction.
- Rescoping the project for this design method underway.
- Engineering will continue through 2025.

West Fillmore Over Unnamed Channel Bridge Replacement
Believed to have been built in the 1970s, the West Fillmore Bridge was a 48-inch diameter corrugated metal pipe located just west of Coronado High School, 25 feet below the roadway. Replacement was needed as the structure had reached the end of its service life. An excavation of this depth presented many challenges and had a significant impact on the traveling public, so the project team evaluated alternative installation methods. The new 72-inch diameter reinforced concrete pipe was bored and jacked approximately 14 feet southwest of the existing pipe. Once the new pipe was completed, the original pipe was filled in and abandoned in place. The proposed crossing was planned to accommodate the future widening of Fillmore Street by designing culvert ends to be easily extended. The PPRTA budget was $3,394,969.
Highlights:
- Project completed and punch list items completed in July 2024 under construction contract amount.
- Construction began January 2024.
Citywide On-Street Bikeway Improvements Phase I
The City’s Comprehensive Plan, Intermodal Transportation Plan, and the Complete Streets ordinance strongly recommend streets be designed to accommodate safe and efficient bicycle travel/access. There are many locations in the city where safe and adequate bicycle travel and access are not provided or need enhancement. Proposed bikeway improvements will continue to improve and construct bike lanes in accordance with the Intermodal Transportation Plan and the City’s Bicycle Plan. Bike lanes will be installed where feasible to close gaps on the existing on-street bike lane network, improve connections from on-street bike lanes to the Colorado Springs trail system and residential/commercial centers, and develop/implement improved signage to provide better wayfinding for bicyclists.
Highlights:
- Multimodal and Mitigation Option Fund trail crossing grant match.
- Bike lane widening on Hancock Expressway
- Tejon Street design

Marksheffel Road Improvements: North Carefree Circle to Dublin Boulevard
The unimproved two-lane road section of Marksheffel Road between North Carefree Circle and Dublin Boulevard currently experiences systemic congestion and delay (particularly at the Dublin Boulevard intersection) and high crash rates (particularly at the Stetson Hills Boulevard, Barnes Road, and North Carefree Circle intersections). Engineering plans (90% level) for Marksheffel Road were initially completed in 2014. The PPRTA Board approved funds in July 2021 to complete the plans and prepare for right-of-way acquisition. The PPRTA Board approved construction funds in June 2022 for an early construction package to start improvements to Marksheffel Road between North Carefree Circle and the Barnes Road intersections.
The first phase of construction focused on the 1.2-mile section between North Carefree Circle and Barnes Road was complete in late 2024 except for paving the top layer of asphalt and placing final lane striping which will occur in late spring 2025. Major construction on Marksheffel Road between Barnes Road and Dublin Boulevard has started and will extend through 2026.
Once corridor improvements are complete, Marksheffel Road will have two lanes in each direction with a center median, improved drainage, and new sidewalks and paths. The project enhances safety by improving sight distance, upgrading the corridor to the latest design standards, and providing designated space for drivers, walkers and cyclists. Travelers are already experiencing reduced congestion with the completion of an additional lane in each direction and turn lanes at the south end of the project.
The project is funded by the voter-approved PPRTA capital projects program starting in 2025. To advance the project, delayed reimbursements to PPRTA 1 and the City’s PPRTA 2 capital traffic programs were budgeted in amount of $30,980,744. The City and El Paso County contributed additional funds between 2022 and 2024, and PPRTA 3 funds are planned to complete the corridor construction.
Highlights:
- Final engineering from Barnes Road to Dublin Boulevard was completed November 2024 and construction will begin in early 2025.
- Construction from North Carefree to Barnes Road was completed November 2024.
- The Barnes Road intersection was lowered in summer 2024 about eight feet to match the new Marksheffel profiles.
Fillmore Street Bridge Improvements and Trail Connections: I-25 to Monument Creek
Replacement of two bridges carrying Fillmore Street east of I-25 over Monument Creek, Pikes Peak Greenway Trail, and the Union Pacific Railroad. The replacement includes improvements on Fillmore Street in the project area to address multimodal needs and traffic congestion, along with connection to the Pikes Peak Greenway trail.
The Fillmore bridges are over 60 years old and were widened in 1971. The current roadway section permits two eastbound and westbound travel lanes with a shared center turn lane and on substandard sidewalk on the south side of the bridges. Recent bridge inspections have noted issues with the current condition of the bridges that include the rocker bearing rotation, structural and scour issues, voids under the slope paving at the abutment of the railroad bridge, along with the bridge deck nearing the end of its functional life. In 2024, the City completed maintenance on the bridge decks to stabilize their condition until they can be replaced in the near future.
In 2022, the City secured a Bridge Investment Program Planning Grant to complete a Planning and Environmental Linkage Study to begin analyzing potential replacement alternatives and begin public outreach for the project. This study will also assist in expediting potential future phases of the project if the City is able to secure additional supplemental grant funds. PPRTA budget is expected to be $40,250,000.
Highlights:
- Held first Public Open House for the presentation of the Draft Purpose and Need Statement.
- Completed Concurrence Point 1 and 2 with FHWA.
- Completed Corridor Conditions Report.
Citywide Traffic Signal System Upgrade
Design and reconstruct dilapidated traffic signal systems across the City.
Highlights:
- Purchase of EVO radar units.
- Upgrades to the El Paso/Uintah intersection.
Citywide Traffic Signal System Maintenance
Highlights:
- Traffic signal equipment purchases.
- New caissons at Hancock/Monica intersection.

Powers Boulevard Extension: Voyager Bridge over Powers Boulevard
The Voyager Bridge over Powers Boulevard project is a part of the overall northern Powers Blvd Extension from SH83 to Voyager Pkwy. It is a PPRTA regional collaborative Priority A project which will connect Powers Blvd with I-25. Powers Blvd currently ends with an at-grade crossing at Voyager Pkwy.
The first portion of the northern Powers Blvd Extension was the completion of the I-25 exit ramp (Exit 155) to Voyager Pkwy. The Copper Ridge Metropolitan District, in conjunction with the City and PPRTA, are replacing the at-grade intersection of Powers Blvd and Voyager Pkwy with an interchange which includes a bridge on Voyager Pkwy over Powers Blvd. PPRTA budget is expected to be $103,000,000 and funding is split proportionately between the City and El Paso County.
Highlights:
- Construction of the Voyager bridge over Powers Boulevard was completed in 2024.
- Engineering for future phases the Powers Boulevard north extension have started.
Roadway Safety and Traffic Operations Phase 1
This program includes corridor and intersection improvements to mitigate existing safety and traffic flow deficiencies and improve traffic signals, signs, school/pedestrian improvements, pavement markings, and other traffic control devices.
Highlights:
- Marksheffel Road improvements.
- Dublin Boulevard widening design.
- Hancock Expressway multi-use trail design.
- Cheyenne Boulevard / Cheyenne Road sidewalk and safety enhancement project.
- Hancock/Chelton roundabout concept.
- Neighborhood traffic management programs.
- Traffic counts and data analysis.
Citywide Pedestrian Transportation Improvements Phase I
Citywide School and Neighborhood Pedestrian Improvements Phase I
These programs are collectively referred to as the Citywide Sidewalk Infill Program. The City’s Comprehensive Plan, Intermodal Transportation Plan, and the Complete Streets Policy strongly recommend streets be designed to accommodate safe and efficient pedestrian access. There are many locations in the city where safe, adequate pedestrian travel and access are not provided. Proposed pedestrian improvements will continue to construct missing pedestrian connections along transportation facilities, schools, and neighborhoods, follow the Operations and Maintenance Division quadrant approach, improve safety, and develop/implement improved pedestrian connectivity.
Notable sidewalks completed in 2024:
- 2,300 linear feet constructed on the north side of West Cheyenne Road from 8th Street to Hulda Lane.
- 1,100 linear feet constructed on the south side of Cheyenne Boulevard from Cresta Road to Omalley Place.
- 600 linear feet constructed on the east side of Woodburn Street from West Cheyenne Road to Cheyenne Boulevard.
A total of 51,000 square feet of new infill sidewalk was installed with the program in 2024.
Citywide Intersection Improvements Phase I
Construct improvements at intersections that will reduce delay, improve air quality, and enhance safety for both motorized and non-motorized traffic.
Highlights:
- US 24/Peterson Interchange roundabout design.
- Marksheffel Road improvements.
- Signal design at Maizeland/Circle intersection.
- Garden of the Gods Road safety improvements.
Emergency Bridge Fund
The Emergency Bridge Fund addresses unfunded bridge needs and provides the City the ability to repair, replace, or rehabilitate a bridge that presents serious deterioration issue or safety concerns to the travelling public. Historically, Emergency Bridge Funds have been invested in replacement design and construction efforts. The funds have enabled the City to leverage other funding sources, advance design efforts on B-List projects, and address serious bridge needs.
Highlights:
- Reached substantial completion of construction of the Hunters Lane over Spring Run bridge.
- Advanced engineering for UPRR over Fontanero Street siding bridge with the A-list UPRR over Fontanero Street mainline bridge replacement project.
- Continued design of the Water Street culvert replacement project over Camp Creek.
- Continued evaluation of the 11th Street culvert over local drainage.
- Provided the local match for Federal Highway Administration Bridge Investment Program grant which was awarded for a planning study to replace the Fillmore Street Bridges over Monument Creek and the Union Pacific Railroad.
- Committed the local match for a second Federal Highway Administration Bridge Investment Program grant for a planning study to replace the Academy Blvd over Platte Avenue bridge.


PPRTA Trail Program
The City’s Parks, Recreation and Cultural Services Department oversees trail improvement projects to include trail paving, capital corridor reconstruction, crossing improvements (at-grade and grade separated), drainage improvements, connectivity enhancements, signage, and related amenities. PPRTA provides funding for A-list Trail projects as outlined below. Parks looks for opportunities to leverage PPRTA funding to obtain grants or other funding sources to assist with overall project costs.
Highlights:
- Pikes Peak Greenway Corridor Improvements:
- Mesa Creek Crossing: Project included trail construction and installation of a 90-foot pedestrian bridge. Construction is complete as of summer 2024. This project was funded with Trails, Open Space and Parks (TOPS) and grant funding.
- Utility Undergrounding (Mesa Creek to Uintah): Utilities in the path of a future trail project have been undergrounded, to make way for future trail. This project is complete as of late winter 2024. The project is in partnership with Colorado Springs Utilities and is also funded by TOPS.
- Monument Creek Stabilization/Pikes Peak Greenway Underpass: Colorado Springs Utilities has completed this project in October 2024 and as part of the project provided creek access and an underpass at Mesa Road for trail users. This was a cost-share project between Parks and Colorado Springs Utilities.
- Legacy Loop: Pikes Peak Greenway: Construction for trail is underway from Mesa Creek confluence, south to Mesa Road, for approximately 0.6 miles of concrete trail connectivity. The project is estimated for early 2025 completion. This is fully funded by the PPRTA.
- Rock Island Trail Corridor Improvements:
- Legacy Loop: Trail reconstruction is complete as of fall 2024. This project provided almost 1.5 miles of trail construction and completed the missing connection between the Pikes Peak Greenway and the Rock Island Trail. The project was funded by Park Land Dedication Ordinance (PLDO) funds, TOPS, and grants.
- Construction of the Rock Island Trail from Sand Creek Trail to Constitution Boulevard is currently in design and slated for construction in 2025. It is funded by a PPRTA and a grant.
- Shooks Run Trail Corridor Improvements: Preliminary engineering for trail reconstruction from East Las Vegas to Pikes Peak Greenway complete. Engineering is progressing and coordination with property owners is ongoing.
- Sinton Trail Corridor Improvements: The final missing segment of the Sinton Trail at 30th Street to Arrowswest is complete as of summer 2023. Design is complete for improvements to the existing trail from I-25 to Garden of the Gods Road and are anticipated for construction for the first phase in 2025.
- Templeton Gap Trail Improvements: The bridge deck was replaced for the Templeton Gap Trail bridge at Mark Dabling and the Pikes Peak Greenway. The damaged bridge deck was removed and replaced with concrete decking. Construction was completed in late summer Additional PPRTA-funded improvements are planned to existing trail from Union Boulevard and westward.